9/26, 06:24 AM

A Reddit post about urgently selling power supplier stocks over Oracle's data center contract issue went viral. What actually happened, and which part of the AI power shortage theme is truly at risk right now?

2026-09-26


Asymmetry of Winners and Losers: It's Oracle, Not Bloom Energy, That Should Be Worried

The Reddit quote (u/Emotional-Breath-838) suggested that "Bloom Energy (BE) was going to supply power but now isn't," but the actual facts are closer to the opposite. Bloom Energy brought its fuel cells online at the Oracle data center in 55 days as contracted and delivered power (Motley Fool, 2026-09-09). What was delayed this time was not Bloom Energy's fuel cells but a 17-mile natural gas pipeline ("Green Chile Project") being built by a separate operator (Energy Transfer). As the New Mexico state government repeatedly rejected right-of-way permits, the start date slipped six months, from August 2026 to February 2027 (BNN Bloomberg, 2026-09-24).

The substance of the "force majeure" notice Oracle sent to developer Blue Owl is a request to defer rent. Oracle's New Mexico data center lease carries a "hell-or-high-water" (pay no matter what) clause, meaning Oracle must pay rent even if the data center is not completed (Wikipedia; commentary by Quinn Emanuel). Oracle is citing the pipeline delay as force majeure and seeking to push back the rent commencement date by up to three years (Motley Fool, 2026-09-24). In other words, the parties actually bearing risk in this case are not Bloom Energy but Oracle itself and Blue Owl, which expects to receive rent on schedule. Oracle's stock fell more than 3% on the day of the notice, and the related loans traded at a discount of 89-91 cents on the dollar (CNBC, Motley Fool, 2026-09-24).

This is not a problem unique to Oracle. Oracle is on the hook for a total of $248 billion in data center leases, up more than 2,200% from two years ago (CoStar, 2026-09-25). Critics point out that if the AI boom fades, this is a structure of paying rent on space that hasn't even been built yet.

Winners and Losers in This Case

PartyActual ExposureSource
Oracle (ORCL)Loser — hell-or-high-water lease burden, stock down 3%+CNBC, 2026-09-24
Blue Owl (lessor)Loser — delayed rent commencementMotley Fool, 2026-09-24
Bloom Energy (BE)Unaffected or even a beneficiary — delivering as contracted, orders from Oracle expandingMotley Fool, 2026-09-09
GE VernovaBeneficiary — gas turbine backlog, named the biggest winner from the AI power shortage24/7 Wall St, 2026-08-04
NextEra and other utilitiesBeneficiaries — expanding power sales contracts with data centersFortune, 2026-06-23

Morgan Stanley estimates US data center power demand of 68GW for 2026-2028, with only 15GW under construction, leaving a 38GW supply gap (Tech Fund, citing Morgan Stanley). The bottleneck lies less in generation itself than in lead times for high-voltage transformers and switchgear, which have stretched to as long as five years.

So, for Investors

  • When news of power infrastructure risk breaks, first check "who failed to deliver on the contract." As in this case, the culprit is often a third-party bottleneck such as permits or pipelines rather than the power equipment maker.
  • The real warning sign is the balance sheets of hyperscalers that rely heavily on pre-purchases and leases, like Oracle, not the equipment makers and utilities that actually supply power, such as Bloom Energy and GE Vernova. If anything, they are closer to beneficiaries of the supply shortage.
  • Separate from next week's Micron earnings, the target restart date for Oracle's New Mexico pipeline (February 2027) is the next calendar trigger for gauging AI infrastructure debt risk.

Sources: Oracle triggers 'force majeure' on New Mexico data centre project, Oracle Wants Protection If Its AI Data Center Is Delayed. Here's What That Changes for Investors., Oracle is on the hook for $248 billion in data center leases, Bloom Energy Delivered Power to an Oracle Data Center in 55 Days, GE Vernova Set to Be Biggest Winner From AI Data Center's Massive Power Shortfall



Related Questions